Project Status Report
Port Morant Health Centre Renovation/Upgrade
Project Location: Port Morant, St Thomas.
​
Project Description: General renovation and upgrade of the Health Centre.
​
Scope: Retiling, repainting, replacement of fixtures and fittings, and roof repair, construction of patient waiting area, landscaping and paving.
​
Cost: JA$27,703,500.00
​
Funding Source: National Health Fund
​
Current Project Status: 92% Complete.
Major items of work on the main building and the extension substantially complete. Additional works underway inclusive of:
Paving, landscaping, roof repainting; water storage facility improvement; correction of identified defects.
​
Projected Outcome/s: Completion and re-operationalisation of the health centre as a modernised, fit-for-purpose facility delivering health care to the target clientele with enhanced capacity, efficacy and reliability.
Yallahs Health Centre Renovation/Upgrade
Project Location: Yallahs, St Thomas
​
Project Description: General renovation and upgrade of the Health Centre.
​
Scope: Retiling; repainting; replacement of fixtures and fittings and ceiling repair, construction of patient waiting area, landscaping and fencing
​
Cost: JA$21,779,667.00
​
Funding Source: National Health Fund
​
Project Start Date: August 24, 2023
Current Project Status: 37% Complete
Fencing in progress; internal refurbishment in progress
Construction of outpatient waiting area to commence
Solution being pursued for relocation of pharmacy.
​
Next Steps: Completion of outstanding work; corrective work as necessary; completion of additional work.
​
Projected Outcome/s: Completion and re-operationalisation of the health centre as a modernised, fit for purpose facility delivering health care to the target clientele with enhanced capacity, efficacy and reliability.
Linstead Health Centre Renovation/Upgrade Project
Project Location: Linstead, St Catherine
​
Project Description: Renovation and Upgrading Works
​
Scope: Reconfiguration of internal spaces; retiling; repainting; replacement of fixtures and fittings; roof repair, fence construction and paving
​
Cost: JA$11,921,900.00
​
Funding Source: National Health Fund
​
Project Start Date: September 18, 2023
​
Current Project Status: 65% Complete
Paving and fencing completed; internal reconfiguration and repair/refurbishment work undertaken; roof repairs required prior to completion of internal works.
​
Next Steps: Completion of roof repairs (additional to original project scope). Continuation of work towards scheduled completion.
​
Projected Outcome/s: Completion and re-operationalisation of the health centre as a modernised, fit-for-purpose facility delivering health care to the target clientele with enhanced capacity, efficacy and reliability​.
Central Village Health Centre Renovation/Upgrade
Project Location: Central Village, St Catherine
​
Project Description: General renovation and upgrade of Type 3 Health Centre.
​
Scope: Repainting; replacement of fixtures and fittings; building extension and repainting, wall construction, gate construction and paving​.
​
Cost: JA$8,694,000.00
​
Funding Entity: National Health Fund
​
Project Start Date: June 3, 2023
Project Status: 100% Complete​
​
Projected Outcome/s: Completion and re-operationalisation of the health centre as a modernised, fit-for-purpose facility delivering health care to the target clientele with enhanced capacity, efficacy and reliability
​
​
Arcadia Health Centre Renovation/Upgrade
Project Location: Arcadia, St Thomas
​
Project Description: General renovation work.
​
Scope: Retiling, repainting, and replacement of fixtures and fittings, de-bushing and fence repair.
​
Cost JA$6,100,000.00
​
Funding Entity: SERHA
​
Project Start Date: September 19, 2023
Current Project Status: ​​
-
Works underway for landscaping, electrical installation and correction of identified defects.
​
Projected Outcome/s: Preparation of the facility to deliver health care under more accommodating conditions, with comfortable and fit-for-purpose facilities for staff and patients.
Rowlandsfield Health Centre Renovation/Upgrade Project
Project Location: Rowlandsfield, St Thomas
​
Project Description: Construction of perimeter fencing together with landscaping of external spaces.
​
Scope: Site clearance; site preparation; erection of chain-link fence; making good works disturbed; landscaping.
​
Cost: JA$2,000,000.00
​
Funding Entity: National Health Fund
​
Project Start Date: December, 2023
Project Status:
-
100% Complete
-
Work was completed in accordance with the scope of work.
​
Projected Outcome/s:
-
Completion of perimeter fencing to enhance safety and security at the health centre.
-
Undertaking external work to improve the aesthetic quality of the installation.
​
Further Remarks:
Project outcomes were achieved.
Morant Bay Health Centre Roof Repair Project
Project Location: Morant Bay, St Thomas
​
Project Description: Waterproofing of the existing concrete roof of the Morant Bay Health Centre.
​
Scope:
-
Removal of existing waterproofing;
-
Effecting repair/corrective work as necessary
-
Installation of new waterproofing;
-
Making good works disturbed;
-
Site cleanup
​
Cost: JA$4,128,450.00
​
Funding Entity: SERHA
​
Project Start Date: May 2, 2023
Current Project Status:
Outstanding work to be done to the roof.
​
Projected Outcome/s:
​Substantial completion was achieved in November 2023, with minor outstanding work and roof repairs to be done.
​
Supply and Installation of Digital X-Ray Machines at SERHA Hospitals
Project Location: Kingston Public Hospital (KPH); Spanish Town Hospital (STH); Bustamante Hospital for Children (BHC) and National Chest Hospital (NCH)
​
Project Description:
Supply and Installation of Six (6) Digital X-Ray Machines:
-
3 at Kingston Public Hospital
-
1 at Spanish Town Hospital
-
1 at Bustamante Hospital for Children
-
1 at National Chest Hospital
​
Scope:
-
Decommissioning and removal of previous X-ray machines
-
Preparatory civil works
-
Preparatory mechanical installation
-
Preparatory electrical installation
-
IT installations
-
Installation of X-ray machines and appurtenant equipment
-
Testing and commissioning
​
Cost: JA$500,000,000.00
​
Funding Entity: Ministry of Health and Wellness
​
Project Start Date: August 31, 2022
Current Project Status:
-
80% Complete
-
Three machines have been installed at KPH; UPS installation is imminent; commissioning to follow (by the second week of April); Machine installation is underway at KPH and STH;
- Installation of machines at BHC and NCH is to be completed in April and May 2024, respectively.
​
Next Steps:
​Continuation of processes of installation and commissioning.
​
Projected Outcome/s:
Equipping of four (4) hospitals with modern digital X-ray machines with a view to improving the efficiency, speed of operation and quality of output in the process of undertaking X-rays and generating and analysing resultant imagery.
​
Princess Margaret Hospital Accident and Emergency Unit Roof Repair Project
Project Location: Morant Bay, St Thomas
​
Project Description:
Replacement of timber and metal roof of the hospital's Accident and Emergency Unit.
​
Scope:
-
Removal of existing roof covering;
-
Replacement of structural members as required
-
Installation of new roof covering;
-
Installation of guttering and downpipes;
-
Making good works disturbed;
-
Site cleanup
​
Cost: JA$5,345,000.00
​
Funding Entity: SERHA
​
Project Start Date: November, 2023
​
Project Status:
100% Complete​
Paving Work to Correct Ground Subsidence - National Chest Hospital
Project Location: National Chest Hospital, St Andrew
​
Project Description:
Undertaking paving works on ground impacted by subsidence in order to provide a stable platform for the movement of heavy vehicles, particularly for the delivery of medical oxygen.
​
Scope:
Site preparation; excavation and earthworks; application of asphaltic concrete pavement; making good works disturbed; clean up and site restoration
​
Cost: $4,678,220.00
​
Funding Entity: SERHA
​
Project Start Date: December 12, 2023
Project Status:
100% Complete​
​
Projected Outcome/s: Ensuring stable ground to support heavy vehicles to ensure the safe transit and operation of medical oxygen and any other necessary services.
Construction of Building to House New Air Compressor & Vacuum System at the National Chest Hospital
Project Location: National Chest Hospital, St Andrew
​
Project Description:
Construction of a concrete building to accommodate a new air compression and vacuum system that is to serve the hospital.
​
Scope:
Site preparation, excavation and earthworks, substructure and superstructure construction, installation of fixtures and fittings, installation of services, finishes, site cleanup, and making good all disturbed works.
​
Cost: JA$5,428,616.00
​
Funding Entity: SERHA
​
Project Start Date: February 8, 2024
Project Status:
-
100% Complete
​
Projected Outcome/s: Adequate accommodation of a newly installed air compression and vacuum system, thereby facilitating and Ensuring stable ground to support heavy vehicles in order to ensure the safe transit and operation in the delivery of medical oxygen as well as for any other necessary services.
​